Plan check is the part of the permit review process where the City carefully reviews the architectural plans you have submitted. Some permits do not have plans so there is no plan check process.
The building permit Plan Check process takes about 15-20 business days (one month calendar) for initial review for residential additions, remodels, new single family homes, grading permits, signs, retaining walls, trellis, pools, patio covers and minor tenant improvements. If a second plan check is required due to non-approvable plans, the second plan check takes approximately 10 business days.
The Plan Check process takes about 20-30 business days (about 2 months calendar ) for first review for all subdivisions, commercial buildings, industrial buildings, major tenant improvements, multi-family homes and all others takes approximately 20 business days. If a second plan check is required due to non-approvable plans, the second plan check turnaround takes about another 10 business days (two weeks calendar)
.
The Building Division Office will notify you when the plan check reviews are complete and when the
application is approved and ready to issue.