When will the Petaluma River be dredged?

Dredging will begin on Friday, September 4, 2020, and will end no later than October 29, 2020. Under the terms of the contract, the contractor has 89 days to complete the project.

The contractor is allowed to work 24 hours a day, 7 days a week. This is a big project with a short timeline so we expect to see crews working day and night, 7 days a week.