Police Station Improvements

Project Description

This project will replace the Heating, Ventilation, and Air Conditioning (HVAC) system at the Police Department.

Traffic Impact

None.

 

Project Status

The project was completed in the Summer of 2020.

BID Details

The Notice Inviting Bids for the construction contract was issued on May 2, 2019. On May 23, 2019, three (3) bids were received as follows:

 

Name of Bidder Business Location  

Total Base Bid

Total Bid Alternate
Air9 Carmichael, CA $79,000.00 $14,500.00
R.J. Mechanical Cotati, CA $64,200.00 $17,612.00
Matrix HG Novato, CA $49,611.00 $14,732.00
Project Estimate N/A $80,000.00  

 

Petaluma Police Department Front
Close window