outlined emergency alert button EMERGENCY ALERT: CORONAVIRUS INFO AND ANNOUNCEMENTS / NOTICIAS Y ACTUALIZACIONES DEL CORONAVIRUS

Petaluma Blvd Guardrail

Project Description

This project includes the installation of approximately 150 feet of guardrail along Petaluma Boulevard South near Gossage Avenue; traffic signal head replacement at 12 intersections; and the installation of rectangular rapid flashing beacons at 12 uncontrolled crosswalks.

Project Manager: Jeff Stutsman – Traffic Engineer

Traffic Impact

The project is currently in the design phase and currently has no traffic impacts

Project Status/Timeline

We anticipate that the design will be completed in March of 2020. Construction will occur in the summer and fall of 2020 when grant funds become available.

Funding

This project is funded through California's Highway Safety Improvement Program

BID Details

The project is being designed in house.

photo of public work employees