Petaluma Blvd Guardrail

Project Description

This project includes the installation of approximately 150 feet of guardrail along Petaluma Boulevard North near Gossage Avenue; traffic signal head replacement at 12 intersections; and the installation of rectangular rapid flashing beacons at 12 uncontrolled crosswalks.

Project Manager: Jeff Stutsman – Traffic Engineer

Traffic Impact

No traffic impacts are anticipated.

Project Status/Timeline

The guardrail portion of the project was completed in January 2021. We anticipate work on the traffic signals and flashing beacons to be completed by April of 2021.

Funding

This project is funded through California's Highway Safety Improvement Program

BID Details

The project is being designed in house.

Petaluma Blvd North Guardrail